NEW CASTLE, Del. — The rebuild of a Delaware bridge expected to be completed last Thanksgiving after initial delays is now expected to extend into March.

Delaware Department of Transportation spokesman C.R. McLeod told The News Journal of Wilmington on Monday those delays have added an extra $1 million to Del. 141 bridge’s cost. Mumford and Miller Concrete Inc. planned to begin construction last summer, but delays pushed the start date to fall.

The discovery of an asbestos conduit by workers slicing into the old structure delayed plans further. Delaware DOT says the conduit wasn’t included in the company’s $15.6 million design plans, but original bridge blueprints from the 1950s, which the company should have referenced, showed it.

A McCormick Taylor employee said they couldn’t comment Monday as the project designer was unavailable.

Information from: The News Journal of Wilmington, Del.,

Author photo
The AP is one of the largest and most trusted sources of independent newsgathering. AP is neither privately owned nor government-funded; instead, as a not-for-profit news cooperative owned by its American newspaper and broadcast members, it can maintain its single-minded focus on newsgathering and its commitment to the highest standards of objective, accurate journalism.